A massive rollout of solar PV with storage has begun for schools in Central Queensland. Schools in the Rockhampton Catholic Diocese, which stretches from Bundaberg to Mackay, and west to Longreach, have contracted for rooftop solar totalling more than 4MW with battery storage of 3MWh.
GEM Energy, the Brisbane-based firm who last year completed Queensland’s first large solar/battery storage school installation at Bundaberg Christian College (200kW solar PV with 250 kW usable storage) started the project roll out in December 2015 in Emerald, Central QLD.
The deal features energy efficiency initiatives across 52 sites ranging from LED lighting upgrades to solar and storage, with systems varying in size depending of the respective school or college requirements.
Although some system designs are still being finalised, and pending council approvals, Jack Hooper, GEM Energy CEO, says that the largest installation could end up being more than 1MW solar PV and over 1.2MWh battery storage. GEM Energy has opted for Q CELLS solar panels, SolarEdge inverters and power optimizers, and Tesla batteries for the roll out.
Over 20 installations have already been completed, including St Patricks Catholic Primary School in Emerald (pictured below).
Pay-back periods for the project costs are expected to be as short as two years for the smaller solar PV-only projects, and up to eight years for the larger projects which have the additional cost of battery-storage.
Jack Hooper says that one of the keys to generating the cost savings is tariff optimisation.
“We look to minimise demand peaks and maximise on-site usage of the “free” power.”
“Schools are a natural fit for solar PV, as the bulk of the metered usage (air-conditioning and lighting) occurs while the sun is shining.
The dispatchable energy from battery storage is important when cloud cover moves in during peak load periods, and for meeting the more modest night-time loads.”
All of the schools remain grid-connected, but as Ergon Energy’s network regulations currently prohibit export-to-grid from installations over 30 kW, generating cost savings while meeting the network operator’s requirements has been a challenge for GEM’s principal electrical engineer, Dimitar Iliev.
“Limiting excess solar production, which is common in schools on weekends and during holidays, to ensure zero grid export, while maintaining smooth battery charging and discharging on projects of this scale is technically very demanding.
Storage batteries add to costs, but assist by soaking up excess solar energy generation”
Hooper adds, “Meeting the design challenges means we can now give school CFO’s the accurate financial and system performance modelling they want before they’ll commit to major spending. Otherwise it’s just a guessing game.”
Acting Director Catholic Education – Diocese of Rockhampton, Ross Jones, is enthusiastic about the rollout.
“The project aligns well with our ongoing endeavours to be proactive in the area of sustainability and care for the environment across our kindergartens, primary schools and colleges.”
The rollout will occur in three phases and is expected to be completed in 2019.
John Elliott is a Science and Maths teacher at a Brisbane public school, and has been active in lobbying the Qld state government to make the (obvious and profitable) step of rolling out large solar PV on government schools, of which there are nearly 1300.
This post was published on July 25, 2017 1:06 pm
Switching water heaters to charge during the day can soak up solar and make sure…
Australia has notched up a new renewable energy milestone, with the number of households around…
A client recently presented us with a challenge: More than 2,000 properties that could have…
A $15m large-scale solar and battery storage rollout across six regional Western Australia towns has…
Australians aren’t signing up to VPPs at the rate the government needs to meet its…
Clean Energy Finance Corporation signs agreement with ING Australia to deliver another low-rate green loan…
View Comments
I have a feeling that there are few people who take the GHG crisis seriously.
Why not plaster all suitable rooftops with pv? Now in NSW the FIT is so good that pv will pay itself off without using electricity behind the meter. ie Net income generation while cutting emissions.
I heard from a Sydney school deputy principal that the Department of Education pays all the bills so individual schools have no financial benefit. And nobody with the time to drive a project.
The DoE canned a project I was involved in.
Qld govt (via DET (Dept. Education and Training) Infrastructure branch) has recently completed a "market sounding" to help develop detail for a tender for state-wide rollout of solar and energy efficiency initiatives. It is true that there is little incentive for individual schools to go solar, as DET pays most bills, but it appears the department has finally got the message that it can cut costs statewide with big solar PV and LED lighting.
Unfortunately, Energex currently prohibits export to grid for systems over 30kW (I want 300 for my school) which is tragic, given that a typical state school is open for around 200 days a year, and closed for 165!
Thats a positive story aside from the Energex limitations