Puerto Rico’s electric system is at a crucial inflection point, with an opportunity to pivot from years of hardship—high energy costs, utility bankruptcy, the largest blackout in US history, and heavy pollution from a system 98 percent powered by fossil fuels—to a new vision that is clean, reliable, and resilient. In March of this year,

Puerto Rico’s new comprehensive energy policy (Act 17) became law, putting forth a vision for a more resilient and distributed system, as well as requiring 100 percent of electric power to come from renewable sources by 2050 and 40 percent by 2025, up from 2 percent today.

Now the details of how that vision could be met are coming into focus, with the utility’s proposed 20-year integrated resource plan (IRP) under review by Puerto Rico’s energy regulator.

This review could wrap up as early as February 2020, with key hearings scheduled for early January. At that point, the regulator can direct the Puerto Rico Electric Power Authority (PREPA) to follow a certain planning scenario or extend the process and ask for more analysis.

The proposed IRP evaluates a wide range of scenarios involving different power plant options and grid configurations, all of which envision significant transformation of today’s system and retiring most of the antiquated power plants burning oil, as well as the island’s coal power plant.

Among all the options presented, there is one primary question that comes through – how much should Puerto Rico’s energy system rely on imported natural gas in the coming decades, and how much on renewable energy to align with the vision in Act 17?

A choice between gas-heavy or solar-focused futures

The IRP analyzes over 30 different scenarios for the island electricity system, but three stand out. PREPA’s preferred plan (labeled “ESM”) includes major new gas investments in the North (San Juan and Palo Seco), West (Mayagüez), and East (Yabucoa), including building LNG import terminals and new power generation at each location.

These are in addition to the existing gas infrastructure in the South (Ecoelectrica) and a new facility under construction in San Juan. PREPA suggests a second scenario (labeled “S4S2”) that is also attractive – this plan leaves out gas at Mayagüez and Yabucoa, relying on slightly more solar energy.

A third scenario (labeled “S3S2S8”) offers a heavy focus on solar investments and minimizes new gas investments. Figure 1 summarizes these three scenarios.

Figure 1: Highlights of three scenarios from PREPA’s integrated resource plan (IRP)

PREPA has made clear that it prefers the first plan.

The utility’s fiscal plan, submitted to the federal Financial Oversight and Management Board, portrays PREPA’s “future state vision” for power generation which exactly reflects this plan.

PREPA has proposed to its regulator that the Yabucoa and Mayagüez projects be considered only as hedges against future uncertainty in new clean options, but in other forums – from the fiscal plan to public statements at energy conferences – PREPA has indicated the full set of gas investments, including Yabucoa and Mayagüez, are central to its plans. Meanwhile, PREPA largely discards the solar-focused plan in its IRP analysis.

Figure 2: PREPA’s vision for power generation, as presented in its approved fiscal plan from June 2019. Red ovals added to highlight major gas plants.
Many of the proposed gas investments are not needed

PREPA depends on gas facilities in the north and south of Puerto Rico. In the south, near Peñuelas, the Ecoelectrica and Costa Sur power plants already burn gas, imported at a nearby LNG terminal, also run by Ecoelectrica. In the north, the San Juan power plant units 5 and 6 are being converted to run on gas, which will be supplied through new LNG import infrastructure being constructed by NFEnergía.

All three plans described above include completing the San Juan project, consolidating the two power plants in the south to one, and establishing a series of smaller mobile gas generators around the island.

PREPA proposes the Yabucoa and Mayagüez gas facilities based on a “preferred plan” that appears to be added to the analysis by PREPA. None of the other scenarios – which used analytical optimization to select power plant investments – include these facilities, meaning that the IRP analysis never showed it was economically valuable to build these power plants and LNG terminals.

This plan is more expensive than alternatives with more renewables. PREPA suggests the Yabucoa and Mayagüez facilities can be useful as a hedge against uncertainty, but its own analysis shows that if energy demand is higher or lower than expected, developing those facilities will cost Puerto Ricans more than other options and won’t comply with renewable energy targets prescribed by law.

PREPA is also pursuing a new gas power plant and import terminal near San Juan at the Palo Seco site. These investments would be in addition to the San Juan 5&6 project currently under construction.

Even though this project remains subject to regulatory review, PREPA has collaborated with other government agencies to initiate a procurement process for a contractor to build it.

In fact, the IRP also does not make a compelling case for the Palo Seco facility.

When comparing S4S2, which includes natural gas, to S3S2S8 (the high renewable option), PREPA’s own analysis shows their aggregate costs are comparable, even without considering the benefits from lower pollution, better participation, and a more flexible system.

This high renewable scenario relies heavily on solar and battery storage, with a modest amount of wind and hydro, supplemented by more limited gas generation. The costs of the scenario largely stem from the new solar and battery element.

PREPA’s base cost projection presumes a future in which solar costs are rising in Puerto Rico.

This contrasts sharply to decades of solar cost reduction and recent projects in the rest of the world, where competitive solar prices in Mexico, Chile, Jordan, Jamaica, and solar and storage prices in Colorado and California are all coming in less than a third of the cost PREPA projects.

If Puerto Rico secures lower-cost renewables, the high renewable energy option will also be far more cost effective for Puerto Rican families and businesses. I

f the expensive Palo Seco plant is forced through instead, the opportunity for that clean pathway will be greatly limited, and the investment in the gas plant could crowd out other options for decades to come.

A choice for the next 20 years

The Puerto Rico Energy Bureau (PREB) has the opportunity to act decisively to drive a massive transformation in Puerto Rico’s energy system, with the opportunity to shape the island’s energy system for the next 20 years.

Options in the IRP include a solar-focused plan for generation that is well-aligned with new policy focused on renewable energy at comparable cost to alternatives that depend on fossil fuels.

Additionally, most of PREPA’s proposed gas investments are unnecessary.

This includes new LNG import terminals near Mayagüez, Yabucoa, and San Juan, and major power plants in the same locations. In particular, the proposed gas plant at Palo Seco is not needed for a reliable, affordable energy system.

Continued procurement activity for this plant is troubling, and the energy regulator can send a clear message that this plant is not approved and utility and government agencies should stop wasting their resources preparing it.

More than two years have passed since Hurricane Maria, and people are still waiting to see the grand visions of a transformed energy system materialize.

There are certainly elements of the IRP that require new guidance from the regulator (for instance, the role of distributed energy resources vs. large-scale plants), but it provides enough clarity around an attractive plan that PREB can move forward without delay in directing PREPA to start implementing this massive transformation.

Time is short.

The pressing need for improving the system means that Puerto Ricans need a plan that works and doesn’t have a bias toward costly projects that could end up weighing down the power sector for decades.

PREPA’s own analysis though shows a pathway forward to that high renewable option, and the people of Puerto Rico deserve the best options on a pathway to an increasingly clean future as required by Act 17. The regulatory body can help guide the way toward seizing them.

Source: Rocky Mountain Institute. Reproduced with permission.

This post was published on December 19, 2019 11:58 am

View Comments

  • In 15 to 24 months Puerto Rico could be installing solar at $0.75 per Watt peak or less, and batteries at $130 per kWh or less. In 21 to 30 months, Puerto Rico could have its own thin solar production plant with annual capacity of 40 GW peak, and could be supplying the entire Caribbean and adjacent mainlands. A new reworking and combining of 1983 and 1995 solar patents by our inventor and NREL respectively has been modeled at 48% efficiency, and the CapX for the plant is just $40 million (it is nothing at all like today's PV plants). The battery factory would cost a lot more, but still pay for itself in a very short time; batteries could be sold from the mainland if the CapX is too high.

  • Surely by now the locals are installing their own domestic off grid solar/battery systems, even just to run the lights and the TV. The cost of diesel -generated power must be enormous.

Share
Tags: Puerto Rico

Recent Posts

Landlords join call for rebates to help renters and apartments get solar and go electric

People who live in apartments are less likely to benefit from solar power or efficient…

April 19, 2024

Solar Insiders Podcast: Australia loses it on solar

Australia falls out of global top 10 solar countries. Plus: GridBeyond's Michael Phelan on the…

April 18, 2024

Home battery upstart takes on Tesla with new spin on lead acid – made in Australia

New Zealand company unveils plans to start making its new-look lead acid home batteries in…

April 17, 2024

New rooftop panel line promises high efficiency and “cradle to cradle” sustainability

Singaporean solar manufacturer launches new line of rooftop solar panels featuring a unique cell design…

April 16, 2024

Home battery rebate gets major boost as demand for solar storage surges

Huge demand sees another $6 million added to the budget for the Battery Booster rebate,…

April 15, 2024

Untapped rooftop solar: Australian homes could save $9.3 billion a year, UNSW study finds

Australian households could save $9.3 billion on energy bills each year by investing in the…

April 14, 2024