Batteries arrive for Horizon's grid-scale "spinning reserve" trial

Published by

WA utility Horizon Power is set to trial the use of large-scale battery storage to meet peak power demand – acting as an alternative to fossil fuel-generated “spinning reserve” – after two batteries capable of delivering up to 2MWh of power arrived in the coastal town of Carnarvon.
In a first-of-its-kind trial for the state, the two 1000kW batteries housed in two 40 foot containers will be connected to the 17MW Mungullah Power Station and used to store energy produced by that station with the primary function of providing back-up power for the islanded power station.

The batteries – provided by Chinese company, Tianjin Lishen Battery – will be tested to see if they can rapidly provide energy in the event of a spike in demand or if an existing back-up generator stops running, potentially saving hundreds of thousands of dollars a year in fuel and maintenance costs.
It’s a function that would have been useful two years ago, when a category three cyclone tore through Exmouth, Coral Bay and Carnarvon leaving blackouts in its wake – a situation Carnarvon Shire president Karl Brandenburg described as “critical” for the town’s 9,000-odd people.
By comparison, the nearby Thevenard Island was kept in power, thanks to its then relatively new solar-hybrid mini grid that not only survived the storm, but continued running throughout, on stored battery power.
“We have a clear aim to embrace new technology and drive the increased uptake of distributed energy and the capability of microgrid technology,” said Horizon Power managing director Frank Tudor on Wednesday.
“The use of (the Carnarvon) battery storage unit means that the cost of providing spinning reserve to supply electrical power for Carnarvon will be significantly reduced as we will be using stored battery energy rather than gas or diesel to provide reserve power,”
Project director Brett Whisson said the trial also aims to investigate how battery storage might be able to support the installation of more distributed renewable energy in the region, which already has one of the highest penetration levels of all of Horizon’s islanded networks, with 121 individual PV installations totalling 1.3MW in capacity.
More specifically, says Horizon, the is a first step towards meeting its commitment to incorporating renewable energy into the 17MW Mungullah Power Station.

This post was published on March 16, 2017 1:50 pm

Share
Published by

Recent Posts

Nothing new under the sun: A long history of missed chances to build sustainable homes

A 1944 report recommended the Australian government should encourage the building of more climate-responsive and…

January 15, 2025

Regulator nets big fish for creation of false solar rebate statements

One of Australia's biggest rooftop solar retailers and installers revealed as the subject of compliance…

January 14, 2025

Will Victoria’s ‘one-stop-shops’ overcome the hurdles facing household electrification?

An update on how Victoria's State Electricity Commission is rolling out their one-stop-shops for home…

December 23, 2024

Solar Insiders Podcast: A roller coaster year in review – and the keys to a smoother 2025

In our final episode for the year, SunWiz's Warwick Johnston on the highs and the…

December 20, 2024

“Nightmare:” Energy tariffs that are blowing out bills, blindsiding consumers

Regulator report finds that little-understood but increasingly common demand tariffs can add up to $800…

December 20, 2024

Hidden cost of rooftop solar? Actually, networks spend next to nothing on managing exports

Have you heard the one about non-solar homes paying the cost to networks of accommodating…

December 19, 2024