Batteries arrive for Horizon's grid-scale "spinning reserve" trial

Published by

WA utility Horizon Power is set to trial the use of large-scale battery storage to meet peak power demand – acting as an alternative to fossil fuel-generated “spinning reserve” – after two batteries capable of delivering up to 2MWh of power arrived in the coastal town of Carnarvon.
In a first-of-its-kind trial for the state, the two 1000kW batteries housed in two 40 foot containers will be connected to the 17MW Mungullah Power Station and used to store energy produced by that station with the primary function of providing back-up power for the islanded power station.

The batteries – provided by Chinese company, Tianjin Lishen Battery – will be tested to see if they can rapidly provide energy in the event of a spike in demand or if an existing back-up generator stops running, potentially saving hundreds of thousands of dollars a year in fuel and maintenance costs.
It’s a function that would have been useful two years ago, when a category three cyclone tore through Exmouth, Coral Bay and Carnarvon leaving blackouts in its wake – a situation Carnarvon Shire president Karl Brandenburg described as “critical” for the town’s 9,000-odd people.
By comparison, the nearby Thevenard Island was kept in power, thanks to its then relatively new solar-hybrid mini grid that not only survived the storm, but continued running throughout, on stored battery power.
“We have a clear aim to embrace new technology and drive the increased uptake of distributed energy and the capability of microgrid technology,” said Horizon Power managing director Frank Tudor on Wednesday.
“The use of (the Carnarvon) battery storage unit means that the cost of providing spinning reserve to supply electrical power for Carnarvon will be significantly reduced as we will be using stored battery energy rather than gas or diesel to provide reserve power,”
Project director Brett Whisson said the trial also aims to investigate how battery storage might be able to support the installation of more distributed renewable energy in the region, which already has one of the highest penetration levels of all of Horizon’s islanded networks, with 121 individual PV installations totalling 1.3MW in capacity.
More specifically, says Horizon, the is a first step towards meeting its commitment to incorporating renewable energy into the 17MW Mungullah Power Station.

This post was published on March 16, 2017 1:50 pm

Share
Published by

Recent Posts

Rooftop solar growth nears record levels, led by Queensland and commercial installs

For a typically slow month, April 2024 has neared record levels of new rooftop solar…

May 2, 2024

Off-grid solar and battery system “twice the size of the MCG” slashes almond farm energy bill

AGL Energy completes installation of a huge stand-alone solar and battery microgrid that will power…

May 2, 2024

Australian made solar panels now available through more than 100 retailers

Australia’s only solar panel manufacturer says its retail network has more than doubled over the…

May 1, 2024

Solar apartments: State opens offer of up to $100,000 to install shared rooftop PV

Solar for Apartments Program offers up to $100,000 to eligible bodies corporate, 50% as a…

April 29, 2024

Home electrification rebate flooded with interest as gas exodus gears up

State government-backed rebate designed to install bulk residential rooftop PV and electric hot water has…

April 29, 2024

Landlords join call for rebates to help renters and apartments get solar and go electric

People who live in apartments are less likely to benefit from solar power or efficient…

April 19, 2024