A 5MW/10MWh lithium-ion phosphate battery energy system installed on Phillip Island off the coast of southeastern Victoria has been switched on, ready to help power the popular tourist destination through holiday peaks.

The Phillip Island Community Energy Storage System, or PICESS, was installed by AusNet Services and its renewables-focused offshoot Mondo Power as the Bass Coast island’s first major step to sourcing 100 per cent renewables.

As One Step Off The Grid reported in October 2021, the project has received up to $55,000 in grants from the Victorian government through its Neighbourhood Battery Initiative grant program.

With the capacity to power more than 8,000 homes for two hours, or 700 homes for one day, the Hitachi battery will replace the diesel generators previously used to shore up the Island’s electricity supply during holiday peaks and annual events like the Australian Motorcycle Grand Prix.

The developers also hope the PICESS project will open up opportunities for further renewables development on the Island, which is best known for hosting the largest Little Penguin colony in the world.

“The population of Phillip Island more than quadruples over summer, which puts a strain on the local electricity network, and at times, leads to power dropping out,” said said AusNet CEO Tony Narvaez at the launch of the battery on the weekend, also attended by Victoria energy minister Lily D’Ambrosio.

“This battery, which in time will be powered by renewable energy, will help solve this issue.”

Totally Renewable Phillip Island (TRPI) and the Energy Innovation Cooperative (EI Coop) have worked closely with AusNet, Mondo, and the Bass Coast Shire Council to deliver the battery.

“This project is the first of its kind on Phillip Island and it has helped us build a greater understanding of how batteries fit into the broader energy transition from coal-generated electricity to renewables,” added Navarez.

“Replacing generators with the big battery will stabilise electricity supply on the Island when it’s needed most.”

The Hitachi 5MW/10MWh lithium-ion phosphate battery energy system has the capacity to power more than 8,000 homes for 2 hours or 700 homes for a day. It is located in a 38m x 34m fenced high voltage compound and is connected to the electricity grid via underground cables.

“Twenty-five local jobs were created in the region during construction, with the project providing Phillip Island residents with new energy job opportunities,” said Mr Narvaez.

This post was published on June 5, 2023 12:20 pm

Share
Published by

Recent Posts

Will Victoria’s ‘one-stop-shops’ overcome the hurdles facing household electrification?

An update on how Victoria's State Electricity Commission is rolling out their one-stop-shops for home…

December 23, 2024

Solar Insiders Podcast: A roller coaster year in review – and the keys to a smoother 2025

In our final episode for the year, SunWiz's Warwick Johnston on the highs and the…

December 20, 2024

“Nightmare:” Energy tariffs that are blowing out bills, blindsiding consumers

Regulator report finds that little-understood but increasingly common demand tariffs can add up to $800…

December 20, 2024

Hidden cost of rooftop solar? Actually, networks spend next to nothing on managing exports

Have you heard the one about non-solar homes paying the cost to networks of accommodating…

December 19, 2024

With just $500 of rooftop solar modules, you could charge your EVs for 20 years

Four good quality solar panels - costing around $500 - would produce enough power for…

December 19, 2024

“It makes no sense:” How fossil gas industry is blocking electrification and consumer savings

The gas war still burns: “We need to think about how to stop misinformation going…

December 17, 2024