Deakin Uni launches renewable microgrid, with Australia’s biggest on-campus solar farm

Published by

A $23 million renewable energy microgrid that includes a 2MWh battery storage system and Australia’s largest on-campus solar farm at 7MW, has been switched on in Victoria by Deakin University.

The microgrid was launched at Deakin’s Waurn Ponds campus in Geelong on Tuesday as the latest “bleeding edge” renewable energy development by a tertiary institution in Australia, following notable efforts by Monash University, also in Victoria, and the University of Queensland, as well as many others.

This particular system, however, does lay claim to the largest solar farm ever built on an Australian university campus, at 7MW, and one of the largest behind-the-meter PV generation assets in the country, too. According to the director of Deakin Energy, Dr Adrian Panow, the microrgid will ultimately supply more than half of the campus’ energy demand.

Panow says the solar component of the microgrid – which was designed and built in partnership with AusNet Services and Mondo Power – combines more than 23,000 PV ground-mounted panels and a further 833 on campus rooftops, including student residences.

“The scale of the … project is important in two ways: achieving our carbon neutral objectives and providing a platform for industry-relevant research,” he said.

“The research focus incorporated into the design of the infrastructure builds on consultation with universities around the world, including Princeton and the University of California at San Diego.”

Deakin says its energy platform has drawn on internationally recognised capabilities and facilities for sustainable energy development across the University, including the Institute for Frontier Materials, BatTRI-Hub, the Institute for Intelligent Systems Research and Innovation (IISRI), and the Faculty of Business and Law.

Beyond its role in research – and, of course, the economic benefits of solar self-generation and consumption – Deakin Vice-Chancellor Professor Iain Martin wants the university to “lead by example” with the microgrid, making a positive contribution in the collective fight against climate change and a big step to the University’s own goal to be carbon neutral by 2025.

“Australia is in a strong position to benefit from moving rapidly in this endeavour, and at Deakin, we believe we have a duty to use our capabilities and assets to demonstrate both ambition and leadership on the issue of renewables,” Professor Martin said in a speech at the microgrid launch.

“We want to be a working example – a ‘living lab’ – of how a large organisation can lead through its actions and fundamentally change its ways of doing. This includes the complete, systemic integration of sustainability across all our activities.

“To achieve a sustainable energy future in Australia, it will require a long-term, cross-sector, collective effort. We require a bi-partisan political commitment over the next few decades; the political and community leadership required will be significant.”

Deakin’s efforts have attracted the attention of the CEO of the Energy Efficiency Council, Luke Menzel, who visited the microgrid a few weeks ago and documented the visit on LinkedIn.

“2MWh battery, largest behind the meter solar farm in the Southern Hemisphere, and big plans to manage onsite loads to match supply. Impressive stuff,” Menzel wrote beneath a photo of the solar project.

“Monash and Deakin, two great EEC members doing bleeding edge work with microgrids, with very different opportunities and constraints,” he added.

Monash, as One Step Off The Grid has reported, has been chipping away at its own hybrid renewables and storage microgrid at its Clayton campus, which once claimed Australia’s biggest behind-the-meter battery system – a 180kW/900kWh vanadium redox flow battery and a 120kW/120kWh C1-rated lithium battery.

The $7.1 million Monash Smart Energy City project – which has won grant funding from both ARENA and the Victorian state government – aims to connect 20 buildings across the Clayton campus and run them entirely on the University’s own smart embedded network of renewables and battery storage, using the Advanced Grid Management software platform of Indra Australia.

The University of Queensland, meanwhile, has built a 64MW solar farm – although not on-campus – and in 2019 flicked the switch on its own 1.1MW/2.2MWh Tesla energy storage system as part of a goal to become 100 per cent renewably powered by onsite generation.

This post was published on April 22, 2021 12:08 pm

Share
Published by

Recent Posts

Will Victoria’s ‘one-stop-shops’ overcome the hurdles facing household electrification?

An update on how Victoria's State Electricity Commission is rolling out their one-stop-shops for home…

December 23, 2024

Solar Insiders Podcast: A roller coaster year in review – and the keys to a smoother 2025

In our final episode for the year, SunWiz's Warwick Johnston on the highs and the…

December 20, 2024

“Nightmare:” Energy tariffs that are blowing out bills, blindsiding consumers

Regulator report finds that little-understood but increasingly common demand tariffs can add up to $800…

December 20, 2024

Hidden cost of rooftop solar? Actually, networks spend next to nothing on managing exports

Have you heard the one about non-solar homes paying the cost to networks of accommodating…

December 19, 2024

With just $500 of rooftop solar modules, you could charge your EVs for 20 years

Four good quality solar panels - costing around $500 - would produce enough power for…

December 19, 2024

“It makes no sense:” How fossil gas industry is blocking electrification and consumer savings

The gas war still burns: “We need to think about how to stop misinformation going…

December 17, 2024