Horizon Power’s poster child for the shift to a distributed renewable grid, the Western Australia Pilbara town of Onslow, says its solar and battery microgrid is already helping to deliver “more reliable” and cleaner power – at levels of up to 90 per cent renewables.
The W.A. regional utility said on Tuesday that the newly commissioned 1MW solar and battery microgrid had notched up some new milestones, including reliability testing, and the first stage of an intelligent control system.
The latter was being tested to ensure that the microgrid integrated effectively with the broader power system, once fully operational.
“We are achieving up to 90 per cent of the power being delivered in Onslow coming from renewable sources with the commissioning of the solar and battery,” a company spokesperson said.
“However, this is not constant and depends on how much demand, time of the day, cloud cover, etc. The expected reduction in CO2 emissions is 820 tonnes a year.”
“Before the commissioning of the solar and battery, we had 100 per cent fossil fuel generation in the town and we are aiming to reach 100 per cent of generation from renewable sources in the town, at certain times of the day and year, as an outcome of this pilot.
“We expect to achieve the highest levels of renewable energy penetration during the middle of the day in the cooler months.”
As we have reported on One Step, Horizon Power’s Renewable Energy Pilot in Onslow – the launching base for the massive Wheatstone LNG project owned by Chevron – combines a new 8MW gas-fired power plant with distributed and utility-scale solar and battery storage.
Horizon Power built the gas plant in Onslow which was commissioned last year, and this year has delivered the solar farm and battery.
Onslow residents have meanwhile been incentivised to install solar and battery at their homes as part of the project which tests the management of renewable energy in an isolated regional community.
Horizon said this week that the microgrid control technology was now being used to reduce power fluctuations, increase power quality and coordinate power generation from gas plant with the solar farm and battery.
“The benefit to the community from this stage of the project is more reliable, cleaner and greener power through the incorporation of utility grade solar and battery assets into the power infrastructure,” said Horizon CEO Stephanie Unwin in comments on Tuesday.
“The microgrid management technology is an amazing piece of technology that is new to this state and allows for the careful management of the various energy sources in the town,” she said.
The solar and natural gas-powered micro-grid was financially backed by Chevron, which has invested more than $250 million in social and critical infrastructure in the community of Onslow as part of its State Development Agreement.
“Investing in the power projects in Onslow means natural gas is partnering with renewables to deliver affordable, reliable and ever-cleaner energy for the town,” Chevron Australia’s Wheatstone Plant Manager Nigel Comerford said.
Sophie is editor of One Step Off The Grid and deputy editor of its sister site, Renew Economy. Sophie has been writing about clean energy for more than a decade.
This post was published on November 26, 2019 2:03 pm
An update on how Victoria's State Electricity Commission is rolling out their one-stop-shops for home…
In our final episode for the year, SunWiz's Warwick Johnston on the highs and the…
Regulator report finds that little-understood but increasingly common demand tariffs can add up to $800…
Have you heard the one about non-solar homes paying the cost to networks of accommodating…
Four good quality solar panels - costing around $500 - would produce enough power for…
The gas war still burns: “We need to think about how to stop misinformation going…
View Comments
Awesome news! a solar battery installed into houses would directly address demand side intermittency, immediately improve grid efficiency and radically reduce carbon emissions.... emissions reductions will happen very quickly with electric cars and residential solar batteries, simply because less than 15% of the calorific content of coal is converted to electricity available at the household power socket
Further reductions would be possible if we were to return to an all DC infrastructure inside the home. Photovoltaic PV generates DC, batteries use DC and any appliance with electronics uses DC. Looked at holistically, an all DC home system might give 40% off “plugloads”
Now let’s think of a town/city block of, let’s say 30 similar homes, each block with it’s own DC microgrid. Each homes energy resources could aggregated by the microgrid and used to charge the coming EV fleet. If the block was still connected back to the big grid, ancillary services could be provided to it for a fee.
Can we go further? Of course. What if we did deep retrofits to the Passive House standard to each of the existing homes further load reductions could be realized, up to 70% of heating and cooling loads.
With these additional steps plus some addition storage might be possible to eliminate the gas generator entirely.
If we were able to safely seal gaps, insulate floor, roof, walls, provide appropriate shading from summer sun, allow sun in during the winter and have the most efficient appliances available they could be 100% much sooner.