W.A. gold miner claims Australian first with wind, solar and battery microgrid

Published by

A hybrid wind, solar, battery and gas microgrid being built to power a Western Australian gold mine has won backing from the Australian Renewable Energy Agency.

ARENA will provide $13.5 million in funding towards the “Australia-first” project that is being built to power the Agnew Gold Mine, owned by a subsidiary of the South Africa-based Gold Fields Group.

The hybrid microgrid will combine a five-turbine, 18MW wind farm with a 10,000-panel, 4MW solar farm and a 13MW/4MWh battery system (BESS), underpinned by a 16MW gas engine power station, and back-up diesel. The all-up cost, including gas and diesel and pipeline, is $112 million.

In a statement on Wednesday, ARENA said the project would mark the first time the Australian mining sector has used wind generation as part of a large hybrid microgrid.

That said, a strikingly similar remote hybrid renewables project – although this one grid-connected – was also tapped for funding by ARENA on Wednesday.

That project, which is combining refurbished (second-hand) wind turbines, with solar and battery storage to power a garnet mine near Kalbarri, is due to be completed by the end of this year.

The Gold Fields project at Agnew – due for completion in 2020, the solar is already installed – is being designed, built and will be owned and operated under a 10-year contract by distributed energy outfit EDL.

The combination of wind, solar and battery is expected to provide the mine with up to 60 per cent of its energy requirements, and – at times – will meet all of its power needs with renewables.

Gold Fields has also committed to use innovative operational practices including dynamic load shedding, renewable resource forecasting and IPP-controlled load management to maximise the use of renewables while ensuring system security.

“The project Gold Fields is undertaking will provide a blueprint for other companies to deploy similar off-grid energy solutions and demonstrate a pathway for commercialisation, helping to decarbonise the mining and resources sector,” said ARENA chief Darren Miller in a statement.

“We’re excited to see more mining companies taking up renewable options and Gold Fields’ project comprising solar, wind and battery is helping to position into a more reliable and sustainable energy supply to call upon for the life of the mine.”

Gold Fields also is installing 8MW of solar and 1MW/2MWh lithium ion battery at its Granny Smith mine, also in W.A. that will be completed by Aggreko later this year.

Gold Fields vice president of operations Graeme Owens told the Energy and Mines conference in Perth the company was looking to add more renewables and more storage at its operations, to save costs and cut emissions.

EDL – which owns and operates the award-nominated Coober Pedy Renewable Hybrid Project, which has at times taken the remote opal mining town in South Australia to 100% renewables (once for a period of 81 hours straight) – said it had seen increasing momentum towards hybrid energy solutions, particularly in remote off-grid locations.

“This project represents a major step in Australia’s journey to sustainable energy and EDL is pleased to be an active contributor in this transition,” said EDL CEO James Harman in comments.

“We have leveraged learnings from demonstrated success in other hybrid renewable projects, which will enable us to provide Agnew Gold Mine with greater than 50 per cent renewable energy over the long term, without compromising power quality or reliability.”

For Gold Fields, the Agnew hybrid microgrid project is about maximising energy security while also minimising energy costs, and cutting the company’s carbon footprint.

EDL is delivering the project in two stages: Stage 1, due to be completed this year, is the new off-grid 23MW power station incorporating 16MW gas and 3MW diesel generation and 4MW solar PV.

Stage 2 includes the wind component (18MW), the battery and an advanced micro-grid control system, with construction recently started and due for completion in 2020.

This post was published on June 19, 2019 1:28 pm

View Comments

  • Well that's pricey, isn't it.

    $27M for the Gas, Diesel and Solar, which makes it $85M for 18MW wind and 4MWh of Batteries.

  • I think that is a waist, as it could have been put into a small out back town that could do with some help, and be a permanent system . Not some company that can afford or will be able to afford it from the profits,and if the company goes broke, its all for nothing.

    • Ronald
      Agnew Gold Mine will chuck nearly $100 million into this project. As it's an Australian first then there is some "proof of concept" work in this project. My hope is that everything that is learnt on this project will then be rolled out to a "small out back town that could do with some help" in the not too distant future.

Share
Published by

Recent Posts

New high-powered battery promises to keep homes cool through blackouts

New range of hybrid inverters and battery systems launches in Australia with ability to run…

May 6, 2024

Ban on solar “nuisance marketing” extends to energy upgrade cold-calls and door-knocking

Participants in the Victorian Energy Upgrades scheme are now banned from unsolicited telemarketing, and face…

May 6, 2024

Rooftop solar growth nears record levels, led by Queensland and commercial installs

For a typically slow month, April 2024 has neared record levels of new rooftop solar…

May 2, 2024

Off-grid solar and battery system “twice the size of the MCG” slashes almond farm energy bill

AGL Energy completes installation of a huge stand-alone solar and battery microgrid that will power…

May 2, 2024

Australian made solar panels now available through more than 100 retailers

Australia’s only solar panel manufacturer says its retail network has more than doubled over the…

May 1, 2024

Solar apartments: State opens offer of up to $100,000 to install shared rooftop PV

Solar for Apartments Program offers up to $100,000 to eligible bodies corporate, 50% as a…

April 29, 2024