Solar and battery microgrid on track to power off-grid town of Jabiru

August 2, 2021 by Sophie Vorrath Leave a Comment

Construction is underway on a hybrid renewable power station – based around solar and battery storage – that will supply the off-grid town of Jabiru in the Northern Territory, which is pinning its future on tourism and services.

The company contracted to build and operate the 50 per cent renewable microgrid, Energy Developments Limited (EDL), said on Monday it had started work on the 4.5MW diesel and 3MW/5MWh battery components of the Jabiru Hybrid Renewable Project, with the 3.9MW solar plant to follow.

EDL said the microgrid’s diesel generators were scheduled to come online by the end of 2021 and the solar farm in early 2022, with the entire hybrid power station expected to be fully commissioned by February 2022.

“Once completed, our hybrid renewable power station will provide Jabiru with at least 50 per cent reliable renewable energy over the long term,” EDL chief James Harman said in a statement.

“We are excited about providing this sustainable energy solution to the people of Jabiru, and are proud to contribute to the Northern Territory’s 50% renewable energy target by 2030.”

As One Step reported earlier this year, Jabiru had been supplied by diesel generators from the nearby Ranger uranium mine operated by Energy Resources Australia, but the mine ceased production, taking the diesel generators out of the equation.

The Northern Territory Labor government held a tender for providers to come up with plans to supply the town with at least 50 per cent renewable supply – as per its territory-wide 2030 target.

In a statement, the NT government said the project – part of its $135.5 million dollar commitment to the Future of Jabiru and Kakadu – would ensure secure, reliable and affordable electricity for local businesses and residents.

“Territorians deserve access to the very best services, no matter where they live,” said NT chief minister Michael Gunner.

“Jabiru is an important town, and the gateway to Kakadu National Park and the West Arnhem Region.

“We are investing millions into Jabiru to transform it into the tourism and services hub we know it will one day be.

“This is just another project we are investing in to create jobs for Territorians and new opportunities for local businesses, which is key to keeping us on track as Australia’s comeback capital.”

Sophie Vorrath
Sophie Vorrath

Sophie is editor of One Step Off The Grid and editor of its sister site, Renew Economy. Sophie has been writing about clean energy for more than a decade.

Filed Under: Off-Grid, Battery/Storage, Solar

Primary Sidebar

Sign up for our weekly newsletter

Emissions Counter

Renew Economy

RSS Energy News from Renew Economy

  • Australia’s most powerful battery flexes muscles with second shock absorber test and biggest every charge
  • Expert committee to assist federal oversight of consumer energy resources, with minister having final say
  • Doctored photos, unsafe installs: Regulators continue crackdown on solar and energy rebate breaches
  • Large 900 MW battery and data centre planned at former nuclear power plant site
  • Setting the standards: Why consumer energy resources deserve a better policy approach than “Ready, Fire, Aim”

RSS Electric Vehicle News from The Driven

  • “We need more fast chargers”, scream people who don’t own an EV. But there are other options
  • First Windrose electric trucks arrive in Australia to run freight between Sydney and national capital
  • Matching EV charging, solar and 3 phase supplies. How hard can it be?
  • New study of more than 500,000 used EVs shows battery health is much better than most people think
  • Audi slashes prices of Q6 e-tron as it relaunches A2 as a battery electric, and “most efficient” model it has ever built

Press Releases

  • Huge luxury Saudi resort goes 100pct renewables with one of world’s biggest batteries
  • How solar + storage can be a game-changer for people with disabilities

Footer

Technologies

  • Solar
  • Battery/Storage
  • Electric Vehicles
  • Energy Efficiency
  • Software/Gadgets
  • Other Renewables
  • Policy
  • Tariffs
  • Contact
  • Advertise with us
  • About One Step Off The Grid
  • Terms of Use
  • Privacy Policy

Copyright © 2026 · OneStep Genesis on Genesis Framework · WordPress · Log in