Huge wind turbine parts complete 630km journey to ground-breaking microgrid

December 5, 2019 by Sophie Vorrath 2 Comments

Australia’s first mining sector project to use wind power as part of a large hybrid renewable microgid is starting to take shape, with the first turbine components arriving on-site in the Western Australia northern goldfields region.

Goldwind said on Thursday that deliveries had begun to the Agnew gold mine site, where five GW140/3.57MW turbines would be combined with an existing 23MW solar, gas and diesel power station, and a 13MW/4MWh battery and control system under construction.

The huge turbine parts, including 60m blades, made the 630km road trip from Port Hedland in what is believed to be the longest such truck-trip for components of this size in the world.

Goldwind announced in July that it had inked a deal to deliver the wind farm component of the microgrid project, which EDL is developing and operating under a 10-year agreement to supply power to the Agnew gold mine, which is owned by the company Gold Fields..

The first stage of the $112 million, ARENA-backed project incorporated a 4MW solar farm, with supply supplemented by a 16MW of gas and 3MW diesel generation capacity.

Goldwind Australia managing director John Titchen said a total of 55 turbine components would be transported to site over the next few weeks, with installation of those turbines to begin “shortly.”

Once the wind power component is complete – EDL says this will be around mid-2020 – the 54MW microgrid is expected to supply the Agnew gold mine with more than 50 per cent renewable electricity.

Concept image of the final project. Credit: EDL

Gold Fields executive vice president Stuart Mathews said last month that he hoped the project would lead to more and more mines integrating renewables into their power supplies.

“This is a significant milestone for both the Agnew gold mine and the broader Gold Fields Group, demonstrating our ongoing commitment to strengthening our energy security, optimising energy costs and reducing our carbon footprint through the adoption of new technologies,” he said.

“We are hopeful that this will also enable other companies to consider the options for decarbonising their operations.”

As noted above, the project has received funding support from the Australian Renewable Energy Agency, which provided $13.5 million in recoupable finance.

Sophie Vorrath
Sophie Vorrath

Sophie is editor of One Step Off The Grid and deputy editor of its sister site, Renew Economy. Sophie has been writing about clean energy for more than a decade.

Filed Under: Battery/Storage, Other Renewables, Software/Gadgets, Solar

Primary Sidebar

Sign up for our weekly newsletter

Emissions Counter

Renew Economy

RSS Energy News from Renew Economy

  • Regulator seeks to prosecute energy giant over lead exposure at retired gas plant
  • SwitchedOn podcast: How one regional community got ahead of renewables disinformation
  • Albanese government must redirect Australia’s near $600 per person annual fossil fuel giveaway
  • Another offshore wind proposal scrapped in WA, but two projects advance in Gippsland
  • Australia’s biggest DC-coupled solar battery hybrid to push PV output into evening peaks

RSS Electric Vehicle News from The Driven

  • Geely’s $A15,000 EV gets to 200,000 produced units
  • EV lobby demands financial penalties as broken public chargers fail drivers
  • Tesla continues to “haemorrhage” losses in Europe, as fleet operators look elsewhere
  • Zeekr’s most anticipated car lands in Europe, Australia to follow
  • 100 autonomous electric trucks begin work in giant Mongolia mine

Press Releases

  • Huge luxury Saudi resort goes 100pct renewables with one of world’s biggest batteries
  • How solar + storage can be a game-changer for people with disabilities

Footer

Technologies

  • Solar
  • Battery/Storage
  • Electric Vehicles
  • Energy Efficiency
  • Software/Gadgets
  • Other Renewables
  • Policy
  • Tariffs
  • Contact
  • Advertise with us
  • About One Step Off The Grid
  • Terms of Use
  • Privacy Policy

Copyright © 2025 · OneStep Genesis on Genesis Framework · WordPress · Log in